Wednesday, July 27, 2011

Brigus Gold reports 80% increase in production in Q2 - Outlook bullish for Q3 and Q4 2011

Toronto Stock ExchangeImage via Wikipedia
Brigus Gold Provides Second Quarter Update Jul, 2011 by Business Wire
 Brigus Gold Corp. ("Brigus" or the "Company") (NYSE Amex: BRD) (TSX: BRD) is pleased to report operating results from the second quarter ended June 30, 2011 and provide an update on continuing progress at its Black Fox Mine.

-- The Black Fox Mine produced 15,688 ounces of gold in the second quarter of 2011 (April to June), an 80% increase over first quarter production. Production was 5% below the expected range for the quarter due to a slower than expected ramp up in production from the underground mine. The Company is making steady progress in building its underground mining workforce in the tight and competitive labour market of Timmins, Ontario. Slower recruitment of qualified staff, along with additional required staffing changes, delayed underground development in the second quarter.

-- For the second quarter of 2011, Brigus processed 181,488 tonnes at an average grade of 2.86 grams per tonne and an average recovery of 94.1%. Over half of the production for Q2 was mined from the Phase 2 open pit while the remainder was split evenly between the underground mine, including development ore, and existing low grade stockpiles.

-- Mill throughput averaged 1,994 tonnes per day during the second quarter and 2,115 tonnes per day in the month of June. -- Ore production from both the Phase 2 open pit and underground mine began at the end of March 2011 and has been ramping up since then. Commercial production was achieved from the Phase 2 open pit in April 2011 and commercial production is expected in the underground mine in July 2011.
-- Underground production is a combination of ore from the four mining stopes that are currently open and lower-grade development ore. Four new mining stopes will be open during the third quarter. Underground production is expected to increase to 800 tpd during the third quarter and approximately 1,000 tpd by year-end. The mine plan calls for 10 to 12 mining stopes to be available by year-end.

-- The Phase 2 open pit is currently providing 1,000 to 1,500 tpd of ore that together with underground production and when necessary, low-grade stockpiles, is maintaining the Black Fox Mill's 2,000 tpd throughput capacity. As higher-grade underground ore production increases through the year, mining from the open pit will continue however lower-grade ore will be stockpiled.

-- Open pit mining was restricted during Q1 2011 while relocation and construction of underground mine infrastructure was completed in the pit area. During Q1, production from low-grade stockpiles was approximately 8,700 ounces of gold as previously reported. With ore provided from both open pit and underground, gold production levels have significantly increased in Q2 and will continue to increase quarter over quarter throughout 2011.

-- The Company announced at the end of June that it would proceed with an initial expansion of the Black Fox Mill, which is expected to be completed, and in service, during the first quarter of 2012. This initial expansion will increase processing capacity at the Mill to 2,200 tonnes per day (tpd). Processing capacity and recovery will be increased through optimization of existing equipment, some equipment additions and elimination of production losses.

-- The Company continues to report excellent drilling results from its newly discovered 147 Zone. The Zone now extends to a vertical depth of 240 metres below surface and remains open in all directions. Drilling at the 147 Zone is progressing as planned with four drill rigs. The fifth drill rig is in-fill drilling the Contact Main Zone located approximately 400 m to the north of the 147 Zone and a sixth rig will be added in early August.

"Production continues to ramp up at the Black Fox Mine," said Rick Allan of Brigus.
"Underground development is still in the early stages. As additional stopes are opened this quarter, gold production will continue to increase. Stronger production and ongoing positive drilling results from our newly discovered 147 Zone are catalysts for a positive second half of the year."

About Brigus Gold
Brigus is a growing gold producer committed to maximizing shareholder value through a strategy of efficient production, targeted exploration and select acquisitions. The company operates the wholly owned Black Fox Mine and Mill in the Timmins Gold District of Ontario, Canada. The Black Fox Complex encompasses the Black Fox Mine and adjoining properties in the Township of Black River-Matheson, Ontario, Canada. Brigus is also advancing the Goldfields Project located near Uranium City, Saskatchewan, Canada, which hosts the Box and Athona gold deposits.

In Mexico, Brigus Gold holds a 100 percent interest in the Ixhuatan Project located in the state of Chiapas that is subject to a letter of intent with Cangold. In the Dominican Republic, Brigus has a joint venture covering three mineral exploration projects that is subject to a letter of intent with Everton Resources.

Cautionary and Forward-Looking Statements
Statements contained in this news release that are not historical facts are forward-looking statements that involve risk, uncertainties and other factors that could cause actual results to differ materially from those expressed or implied by such forward-looking statements. All statements regarding the ability of the Company to achieve targeted gold production at its Black Fox Mine, including underground production, and cash costs, meet capital construction schedules and costs, and the continuation of a rising gold price are forward-looking statements and estimates that involve various risks and uncertainties. This forward-looking information includes, or may be based upon, estimates, forecasts, and statements as to management's expectations with respect to, among other things, the issue of permits, the size and quality of the company's mineral resources, progress in development of mineral properties, future production and sales volumes, capital and mine production costs, demand and market outlook for metals, future metal prices and treatment and refining charges, and the financial results of the Company.

Important factors that could cause actual results to differ materially from these forward-looking statements include environmental risks and other factors disclosed under the heading "Risk Factors" in Brigus Gold's most recent annual report on Form 10-K filed with the United States Securities and Exchange Commission and elsewhere in Brigus Gold's documents filed from time to time with the Toronto Stock Exchange, the NYSE Amex Equities, the United States Securities and Exchange Commission and other regulatory authorities. All forward-looking statements included in this news release are based on information available to the Company on the date hereof. The Company assumes no obligation to update any forward-looking statements, except as required by applicable securities laws.

SOURCE: Brigus Gold Corp.
Brigus Gold Corp. 
Jennifer Nicholson CA 
Vice President, Investor Relations 
902-422-1421 
ir@brigusgold.com
Enhanced by Zemanta

Friday, July 22, 2011

Nautilus Minerals is leading the undersea mining business of the 21st century.

Nautilus Minerals Inc.
Nautilus Minerals Inc.

TSX : NUS
AIM : NUS



July 22, 2011 08:31 ET

Nautilus Awarded Exploration Tenements in Eastern Pacific



VANCOUVER, BRITISH COLUMBIA--(Marketwire - July 22, 2011) - Nautilus Minerals' (TSX:NUS)(AIM:NUS) Tongan subsidiary, Tonga Offshore Mining Ltd. ("TOML"), has become one of the first private sector organizations to be granted exploration licences in the highly prospective Clarion Clipperton Zone ("CCZ") of the Eastern Pacific.

Sponsored by the Tongan Government, TOML has been granted approximately 75,000 km2 of prime exploration territory in the CCZ, which lies in international waters between Hawaii and Mexico.
As a result of exploration conducted in the 1980s, the CCZ is known to host significant deposits of polymetallic nodules, which are golf ball sized nuggets, rich in copper, nickel, manganese and cobalt, lying on the seafloor in water depths starting at 4500 metres.

The International Seabed Authority, which is the organization responsible for administering activity on the seafloor in international territory, made the historic decision to grant the TOML licence at its annual meeting in Jamaica this week. The licence is for an initial period of 15 years.

Nautilus CEO Steve Rogers said the award of the exploration permit presented exciting opportunities for the long term growth and expansion of the company.

"At Nautilus, with our first project at Solwara 1 in the Bismarck Sea, (Gold) we are adapting technologies to access seafloor mineral resources in water depths of 1600 metres. Ultimately, we intend to seek to establish the capacity to expand operations to undertake larger scale projects envisaged in the deeper waters of the CCZ.

"Nautilus is pleased to be at the forefront of development, working with industry and the scientific community to establish methodologies and processes to develop these significant resources in ways that are socially and environmentally responsible," he said.

The ISA previously has awarded eight exploration permits to government entities for polymetallic nodule exploration, but has not previously granted licences to private sector organizations. TOML's application for exploration permits represented "a new milestone in the life of the (International Seabed) Authority," according to ISA Secretary General Nii Allotey Odunton.

Links
Map of TOML's tenements: www.nautilusminerals.com/i/pdf/TOMLJuly2011.pdf

About Nautilus Minerals Inc.
Nautilus is the first company to commercially explore the ocean floor for polymetallic seafloor massive sulphide deposits and is currently developing its first project at Solwara 1, in the territorial waters of Papua New Guinea in the western Pacific Ocean. Nautilus is listed on the TSX and AIM stock exchanges, and has among its largest shareholders two of the world's leading international resource companies Anglo American (11.1%) and Teck Resources (6.8%), as well as Metalloinvest, one of the largest and fastest growing mining and metallurgical holding companies in Russia, which beneficially owns 21.0% of the Company's issued shares through Gazmetall Holding (Cyprus) Limited.

Neither the TSX nor the London Stock Exchange accepts responsibility for the adequacy or accuracy of this press release.

Contact Information


Nautilus Minerals Inc.
Investor Relations
+1 (416) 551 1100
investor@nautilusminerals.com

Nautilus Minerals Inc.
Joe Dowling
Vice President Investor Relations and Communications
+61 (7) 3318 5544 or Cell: +61 431 365 741
jjd@nautilusminerals.com
www.nautilusminerals.com

Numis Securities Limited
John Harrison
Nominated Adviser
+ 44(0) 20 7260 1000

Numis Securities Limited
James Black
Corporate Broking
+ 44(0) 20 7260 1000
Enhanced by Zemanta

Thursday, July 14, 2011

Talison Lithium Announces Preliminary Fiscal Year 2011 Production Results



Perth, Western Australia, July 14, 2011Talison Lithium Limited (“Talison” or the “Company”) (TSX:TLH) today announced its preliminary sales volume and production results for the three months (“Q4 2011”) and the twelve months (“FY2011”) ended June 30, 2011.  The Company also provided an update on its three growth projects encompassing progress in its Australian capacity expansion, lithium minerals conversion plant and South American salar exploration program.


 Preliminary Results




Robust Growth in Sales Volume and Record Production

Compared to the previous year, FY2011 sales volume increased 32% to 339,501 tonnes lithium concentrate (or approximately 50,000 tonnes lithium carbonate equivalent (“LCE”)).  FY2011 production was 342,097 tonnes lithium concentrate (approximately 51,000 tonnes LCE), a 30% y/y increase.  

Compared to the year-earlier period, Q4 2011 sales volume increased 5% to 92,416 tonnes lithium concentrate (approximately 14,000 tonnes LCE).  The Company produced a record 89,505 tonnes of lithium concentrate in Q4 2011 (approximately 13,000 tonnes LCE), a 25% y/y increase. Sales of lithium concentrates are made in large shipments to customers and consequently this may result in variations between production and sales in individual quarters.
The sales volume and production figures represent continued robust growth for Talison.  The Company’s Greenbushes Lithium Operations is fully utilizing the new capacity created both by its Stage 1 Expansion and ongoing process improvement programs.  Demand remains strong for all of the Company’s technical and chemical grade lithium concentrate products and Talison continues to maintain its dominant position in the rapidly growing Chinese lithium market.

Peter Oliver, Chief Executive Officer, commented, “We are extremely pleased with the growth in our sales volume and production.  The Greenbushes Lithium Operations is the highest grade lithium mineral resource in the world, and completion of the current expansion will ensure Talison is highly leveraged to a stronger lithium price in a world where security of supply is expected to become increasingly important as governments look to reduce reliance on oil imports and decrease carbon dioxide emissions.”
 
Guidance for Fiscal 2012
During fiscal year 2012, Talison expects that demand will remain strong for its entire suite of products. A full year contribution from the Stage 1 Expansion of the Greenbushes Lithium Operations is anticipated and Talison expects both production and sales to be capacity constrained until completion of the Stage 2 Expansion in Q4 fiscal year 2012.

Peter Oliver added “We are very optimistic about the outlook for Talison as a result of the rapidly changing supply/demand dynamics developing in the lithium industry.  Recent substantial price increases from other lithium suppliers are reflective of a tightening in supply conditions while global demand remains strong.  In anticipation of sustained growth in lithium consumption, driven primarily by the secondary lithium battery market, Talison is investing heavily in its three growth projects.

Growth Projects
Greenbushes Stage 2 Expansion On Schedule and On Budget
The Stage 2 Expansion at the Greenbushes Lithium Operations is proceeding on schedule and on budget.  Earthworks are largely complete, concrete was poured for the finished product stockpile, and the foundation framework for the two new ball mills is being erected.  The Company continues to expect commissioning of the Stage 2 Expansion during the second calendar quarter of 2012 (fiscal Q4 2012).  Upon completion, the Stage 2 Expansion will double the current production capacity at Greenbushes.  Total nameplate production capacity will increase to approximately 740,000 tonnes per annum lithium concentrate (approximately 110,000 tonnes per annum LCE).

Proposed Minerals Conversion Plant
Responding to growing global demand for an additional secure supply of lithium carbonate, particularly from electric vehicle battery manufacturers, Talison is focusing heavily on its proposed plant to convert lithium minerals into lithium carbonate (“Minerals Conversion Plant”). Plant capacity is proposed to be 20,000 tonnes per annum LCE in the first stage, and an additional 20,000 tonnes per annum LCE in the second stage. 

Basic engineering and location studies for the Minerals Conversion Plant have commenced. The location study is evaluating several Western Australian locations, including at the Greenbushes Lithium Operations, and one overseas location. An external engineering consultant has been appointed to expand on previously completed scoping studies and prepare an updated estimate of capital costs. Discussions with potential customers regarding future lithium carbonate requirements and specifications are also underway. 

Talison has employed additional technical and marketing personnel to drive this project.  Based on its analysis of the supply/demand conditions in the lithium industry, the Company is targeting commissioning for the Minerals Conversion Plant in fiscal year 2015.

Salares 7 Project – Second Phase Exploration Program
Following the receipt of outstanding results for both lithium and potassium from the initial drilling at the Salares 7 Project in Chile, Talison is accelerating its exploration program. Talison is currently designing the next phase (Phase 2) of its exploration program and a new custom built sonic drill rig with specific capabilities to suit the ground conditions at the Salares 7 Project is being assembled.

The Phase 2 exploration program will commence in the next Chilean field season and Talison expects to invest approximately US$5 million on the program in fiscal year 2012.  The Phase 2 program includes further drilling at Salar de la Isla, sufficient to form the basis for a potential lithium mineral resource estimate, as well as additional drilling at Salar de Las Parinas, and initial drilling at Salar de Aguilar and Salar Grande.  

Talison is also initiating process test work studies to assist in designing a processing facility for the project, and collecting baseline environmental data, an activity that will need to continue for several field seasons, to be incorporated into the facility permitting procedures.

To view the entire press release please visit:
http://www.talisonlithium.com/media/17459/110714_tll reports fourth quarter production results.pdf



Please find the updated Talison Corporate Presentation contained in the link below:
http://www.talisonlithium.com/media/17020/tlh_investor presentation 4 may 2011.pdf

Please visit our website at:
http://www.talisonlithium.com/
Enhanced by Zemanta

Wednesday, July 13, 2011

Rodinia Lithium Announces Up to 1,800 mg/L Lithium from Aquifer I Pit Sample Results

Rodinia Lithium Inc.Rodinia Lithium Inc.

TSX VENTURE : RM
OTCQX : RDNAF




July 13, 2011 07:30 ET


- Brine Samples from Surface Pits Return Grades Up to 1,800 mg/L Lithium and 13,000 mg/L Potassium 

- Samples Taken from Surface Pits Resulting from Mining of Ulexite

- Represent Highest Grade Sample Results from Diablillos

- Samples Were Taken from Aquifer I, Opening Up the Potential to Recover the Brine from This Aquifer by Open Pit or Trenching


TORONTO, ONTARIO--(Marketwire - July 13, 2011) - Rodinia Lithium Inc. ("Rodinia" or the "Company") (TSX VENTURE:RM)(OTCQX:RDNAF) is pleased to announce results from an additional surface sampling program at its Salar de Diablillos project ("Diablillos" or "Salar") located in Salta Province, Argentina. Results from three large surface pits, a result of current surface mining of ulexite within the top three meters of the Salar, returned high grade values of lithium ("Li"), potassium ("K") and boron ("B"). In particular, samples P8 and P9 returned the highest lithium values sampled on the Salar, with values up to 1800 mg/L Li, 13000 mg/L K, and 990 mg/L B.

William Randall, President & CEO of Rodinia, commented, "The results from these samples are a very pleasant surprise as they are considerably higher grade than our previous surface sampling program, performed with an auger drill. What makes these samples even more encouraging is the fact that they were collected following a period of intense rainfall, possibly the largest in recorded history, meaning that these samples have probably not been further concentrated from their original geochemistry. This is a major development in the definition of Aquifer I. We will now look at the possibility of developing this aquifer through a series of pits or trenches, in a similar way to the brine potash mines of the Utah Salt Flats. Management remains optimistic that this may potentially provide the Company with high grade, low cost initial production with respect to the Salar."

Table 1 – Results from pit samples P7, P8 & P9 – All samples taken in the same area of the Salar.
Sample Li (mg/L) K (mg/L) B (mg/L) Mg:Li SO4:Li
P7 590 6100 650 4.41 16.44
P8 1800 13000 840 3.39 6.67
P9 1400 13000 970 3.36 8.57
The pit samples maintain the favourable geochemistry of the Salar's brine, which is characterized by low magnesium to lithium ratios and distinctively low sulphate to lithium ratios. Lower sulphate levels can reduce the need for expensive reagents, such a calcium chloride ("CaCl2"), during the conventional evaporation processing techniques expected to be employed at the Salar.

The Project is supervised by Ray Spanjers, Rodinia's Manager of Exploration. Mr. Spanjers is considered a qualified person, as defined by National Instrument 43-101, and has reviewed and approved the scientific and technical information in this release. According to the Company's sampling protocol, sample size is to exceed 500 millilitres and is stored in clean, secure containers for transportation. The prepared samples are then forwarded to the ALS Laboratory Group, Environmental Division, in Fort Collins, Co (USA) for analysis. A rigorous QA/QC program is implemented consisting of regular insertion of standards and blanks to ensure laboratory integrity.

About Rodinia Lithium Inc.:
Rodinia Lithium Inc. is a Canadian mineral exploration and development company with a primary focus on Lithium exploration and development in North and South America. The Company is also actively exploring the commercialization of a significant Potash co-product that is expected to be recoverable through the lithium harvesting process.

Rodinia's Salar de Diablillos lithium-brine project in Salta, Argentina, contains a recoverable resource of 2.82 million tonnes lithium carbonate equivalent and 11.27 million tonnes potassium chloride equivalent. The project contains a recoverable inferred resource of 952,553,000 m3 grading 556 mg/L lithium and 6,206 mg/L potassium. Throughout 2011, Rodinia will focus on continuing to develop the Diablillos project by completing additional drilling and advancing through scoping study. More information on the Company's recoverable resource estimate can be found on its SEDAR filing page at www.sedar.com.

The Company also holds 100% mineral rights to approximately 70,000 acres in Nevada's lithium-rich Clayton Valley in Esmeralda County, and is currently in the process of assessing the size, quality and processing alternatives of this deposit. The Clayton Valley project is located in the only known lithium-brine bearing salt lake in North America, and looks to represent the only new source for domestic lithium carbonate supply.
The Projects are supervised by Ray Spanjers, Rodinia's Manager of Exploration. Mr. Spanjers is considered a Qualified Person, as defined by National Instrument 43‐101.

Please visit the Company's web site at www.rodinialithium.com or write us at info@rodinialithium.com.
Cautionary Notes
Except for statements of historical fact contained herein, the information in this press release constitutes "forward-looking information" within the meaning of Canadian securities law. Such forward-looking information may be identified by words such as "plans", "proposes", "estimates", "intends", "expects", "believes", "may", "will" and include without limitation, statements regarding the impact of the drill program and surface sampling program at the Diablillos property and results of such programs; the potential of the Diablillos property; the potential results and timetable for further exploration with respect to the Clayton Valley project and the Diablillos property, the timetable with respect to future acquisitions and exploration developments at Clayton Valley and Diablillos, timetable for further exploration, analysis and development, title disputes or claims; and governmental approvals and regulation. There can be no assurance that such statements will prove to be accurate; actual results and future events could differ materially from such statements. Factors that could cause actual results to differ materially include, among others, metal prices, competition, financing risks, acquisition risks, risks inherent in the mining industry, and regulatory risks. Most of these factors are outside the control of the Company. Investors are cautioned not to put undue reliance on forward-looking information. Except as otherwise required by applicable securities statutes or regulation, the Company expressly disclaims any intent or obligation to update publicly forward-looking information, whether as a result of new information, future events or otherwise.
NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.
Enhanced by Zemanta

Tuesday, July 12, 2011

Rodinia Lithium notice to shareholders, July 11, 2011

Shareholder Letter – July 11, 2011
Dear SHAREHOLDERS,

In response to Rodinia Lithium Inc.'s (“Rodinia” or the “Company”) letter to shareholders dated June 1, 2011, set out below, the Company received a written response from a shareholder containing various questions raised from the corporate update provided by the Company.   As such correspondence refer to comments raised in an on-line discussion board with a number of other current investors in Rodinia and given that the questions are shared by more than a few investors, management of the Company would like to take this opportunity to address such questions and comments and provide a response to all of its shareholders.  Accordingly, we have set out a Q&A style update we hope will serve to universally respond to the issues raised.
Please note such questions are based on comments and questions received from shareholder correspondence, however, for the purpose of this update have been reworded slightly where applicable to fit the context of this update.

Q: In the June 1st letter, the Company discussed the Preliminary Economic Assessment ("PEA") and stated that the PEA was initiated for Diablillos on April 4, 2011 and goes on to say “We are in the process of entering into various engagement letters with the appropriate consulting groups involved in this process.”  The two months between April 4th and June 1st appear to be a sufficient amount of time to hire consultants to conduct the PEA.  Why has there been such a long delay in hiring a contractor?

RM: Rodinia has all the necessary contracts in place to complete the PEA.  Further, work is well underway with these consulting groups towards the completion of the PEA.  Information on the results of the PEA and certain steps within the PEA process will be disclosed once such information is available.  At that time we will also disclose, where appropriate, which consulting groups have been involved in completing the work.  We are confident that we have hired the best the industry has to offer and the quality of the work will become evident as we develop the Salar de Diablillos.

Q: In the June 1st letter, the Company states: “To date we have spent one-on-one time with over eight analysts; five analysts have spent time visiting our project sites and another three are in the process of scheduling visits.”  How long ago did the Company initiate contact with the eight analysts?  When did the five analysts visit the Diablillos project site?  Do you anticipate more analysts, which have visited Diablillos, to initiate coverage of the Company? If so, when do you think this might happen?

RM: Rodinia is continuously looking to engage additional analysts to increase our coverage.  Initial site visits occurred during the first half of 2010, starting with Jon Hykawy of Byron Securities.  Jon initiated coverage shortly thereafter and the team at Byron has been very supportive ever since.  Thereafter, a team at Genuity Capital Markets initiated coverage.  Unfortunately for the Company, Genuity was acquired by Canaccord Financial and both the analyst team at Genuity and the team we were engaging at Canaccord moved on to new firms and new roles where lithium coverage was no longer part of their mandate.  On a positive note, however, the Company was pleased to learn that David Talbot at Dundee Securities initiated coverage on Rodinia on June 9, 2011.  In addition to coverage initiated by Byron and Dundee, the Company also has research coverage from UBIKA and from RB Milestone Group.  We are working diligently to attract a broader research following and anticipate additional initiating reports within 2011.  While the Company is hopeful that such coverage will be initiated, it is important to note that investment banking research coverage is completely independent of Rodinia. 
It is also worth noting, that as of the date of this Q&A, and using Bloomberg as the source for investment banking research coverage, the junior lithium comparator group of eight companies listed on slide 22 of our corporate presentation, has an average following of 2.37 analysts (range zero to four).  With two currently publishing on Rodinia, and having lost a third to industry changes, management believes it has been successful in attracting the necessary coverage and will endeavour to attract a broader research following where applicable.

Q: With a rough, projected production of 10,000 tonnes per year from Diablillos, how many customers in the Lithium market are thought to be necessary for the Company?  Is Shanshan part of this projected market or is this organization solely working to develop the research and engineering for resource extraction from Salar deposits?  Is an off-take agreement with Shanshan anticipated?

RM: Our relationship with Shanshan remains strong and management expects this relationship to continue to evolve as we further develop the project.  Shanshan is a significant end-user of lithium carbonate and not a mining company with research and engineering expertise.

Q: Could the Company provide an update regarding the progress of the Clayton Valley project?  As this is now Q2 2011, are we to expect that these objectives are behind schedule, and if so, any reasons for the delay?  Does the Company project a new timeline for these events (i.e. permitting, drilling, Feasibility Study, pilot plant, financing, construction) be completed?

RM: Clayton Valley is experiencing delays due to drill permitting issues.  The Company expects to resolve these issues shortly and complete additional drilling and the resource estimate by the end of this year.  The delays experienced are unfortunate and we are doing everything in our power to commence drilling on the project again.  Clayton Valley remains one of the Company's key assets and management is working diligently to continue exploration and unlock its potential value for shareholders.

Q: The Company has indicated that it is currently well financed for the majority of the work planned for 2011.  What type of financing is the Company interested in pursuing towards the end of 2011?  Is the Company considering equity, debt or another partner?  When does the Company anticipate this financing?

RM: Rodinia monitors its capital needs very closely and assess financing opportunities as they are needed or presented to the Company.  At this point, the Company does not anticipate requiring additional financing in the near term.  When required, Rodinia will attempt to secure the necessary financing to develop the projects with a view to minimizing the dilutive impact to current shareholders.  It is our aim to reach production in as short a time period as possible without overly diluting the Company.  We believe we will demonstrate this strategy as we continue to develop.

Q: Does the Company envision taking its properties to production or does it hope for the properties to be bought out pending successful results of respective Bankable Feasibility Studies?

RM: Rodinia does not speculate on market activity, nor does the Company chase projects that we don’t believe have the potential to become important lithium producers.  We intend to develop these assets with the clear mandate of putting them into production.  We have compiled a team of the industry’s top experts to ensure timelines are met and the most efficient and profitable production facilities are built and operated.

Q: Does the Company have an opinion as to why current SP has declined so dramatically since the last refinancing and why the current SP languishes in an apparently moribund state?  While global economic uncertainty has been factors in investment, it does not explain much of the current SP value relative to other Lithium Juniors.

RM: We are wholeheartedly disappointed with the share price performance thus far in 2011.  We believe we are working very hard and most importantly achieving the right results with the project, however, these efforts are not reflected in the share price.  We believe that much of the downward pressure on the stock has come as a result of global economic uncertainty and the flight of investment capital away from junior names in lesser known commodities like lithium to liquid gold names or into cash.  In addition, the Company believes that it may have suffered from an increasingly cautious junior lithium market which management believes may have resulted from the material restatement of one of our competitor's initial resource estimate. While the Company cannot foresee complications our competitors may have, management remains optimistic that it is developing its properties with view to unlock the potential value for its shareholders.
Our goal is to be a leader in the junior lithium market and we will continue to strive to achieve this.  Since our last financing, we see as ourselves as middle-of-the-pack performers.  This is not where we want to be and we hope to demonstrate, in the near future, multiple reasons why we should be a leader.

Q: What is the type and amount of proposed production of lithium and potash targeted at this stage by the Company?

RM: Initial production estimates are between 10,000 to 15,000 tpa LCE.  The facilities will be scaled upwards as warranted and as applicable.
Q: When will RM have a good idea about the economics (e.g. costs per tonne and revenues per tonne) of the proposed production levels?

RM: These items will be addressed initially in the upcoming PEA scheduled for the second half of this year.  These parameters will be further refined during the subsequent Feasibility Study.
With respect to revenues per tonne, we draw your attention to a press release issued by FMC Lithium on June 23, 2011 announcing a 20% price increase for lithium carbonate effect July 1, 2011. http://www.prnewswire.com/news-releases/fmc-lithium-announces-global-price-increases-124446383.html

Q: Could the Company elaborate on some of the ideas around the level of production and time? I understand that, at a production level of 10,000 to 15,000 tonnes per year of lithium carbonate, there could be as much as 400 years of resource extraction given current indications of resource.  This timeline does not appear to be beneficial from a Net Present Value perspective to shareholders.

RM: 15,000 tpa represents over 10% market share at this time.  While forecasts show demand increasing over the next ten years, it is Rodinia’s policy to begin with a reasonable level of market participation.  The Company anticipates it will be able to increase production as demand increases.  Management believes that a more conservative approach to its production level targets will assist in reducing higher capital expenditures associated with much larger production, which the Company hopes will ultimately benefit shareholders in the long term.

Q: In light of the announcement made by the governor of Jujuy Province in March 2011, has the Company approached the authorities in Salta Province to seek assurances that they are not planning a similar move in declaring lithium a strategic material and if so what was their response?

RM: While management has had private conversations with Salta’s mining authorities, Salta has publically expressed their position in regards to this issue stating on several occasions that they do not plan to follow Jujuy’s footsteps.  In fact, Salta has publically frowned upon its neighbouring Province's policies calling them “unsound”.
We said it last month but feel it just important to reiterate now – as a team, our top priority is the successful development of our lithium projects.  An extension of this priority is making sure that our efforts are accurately reflected in our share price.  While we are disappointed with recent trading, we maintain our positive attitude and are working hard to develop the company and to unlock value for shareholders.  With the work we continue to complete, the news flow that will follow our recent initiatives (drill results, processing work, etc.), and support from new and existing shareholders such as the individual who took the time to compile the list of questions set out above, we remain highly motivated to continue to grow the Company and execute our strategic plan.

Thanks again for your continued support.
Sincerely,

RODINIA LITHIUM INC.

Farhad Abasov – Executive Chairman
Aaron Wolfe – VP, Corporate Development
William Randall – President & CEO
Jennifer Wagner – Corporate Secretary
Ryan Ptolemy – Chief Financial Officer
Investor Cubed Inc. – Investor Relations

June 1, 2011
Dear SHAREHOLDERS,
On behalf of Rodinia Lithium Inc. (“Rodinia” or the “Company”), we would like to express our appreciation of your ongoing support as a shareholder, and share with you our excitement and vision for the Company as we continue to develop the Salar de Diablillos Project (“Diablillos”).
Despite challenging times in the global capital markets, we were able to close an $11.5 million bought deal equity financing on February 8, 2011.  Since that time, we have been extremely busy.  We have taken numerous steps towards the development of the Diablillos project in Salta Province, Argentina.  In doing so, we have been actively deploying the funds raised to further the project in hopes of generating returns for shareholders.  Notably:
  • Defined an In-Situ Inferred Brine Resource.  On March 2, 2011, we completed our initial inferred brine resource estimate under the guidelines of National Instrument (“NI”) 43-101.  This initial inferred brine resource estimate was independently completed by the internationally recognized, professional engineering and consulting firm AMEC Internacional Ingenieria y Construccion Limitada (“AMEC”).  At that time, we proudly press released 4.9 million tonnes of lithium carbonate equivalent inferred resource and 19.8 million tonnes of potassium chloride equivalent inferred resource.  This resource estimate positions Diablillos amongst the premier lithium and potash bearing salars in the world.

  • Defined a Recoverable Inferred Brine Resource.  On April 1, 2011, one month after releasing an in-situ inferred brine resource at Diablillos, we completed additional work and analysis to define a recoverable inferred brine resource estimate.  This work was again completed independently by AMEC.  The recoverable inferred brine resource was 2.8 million tonnes of lithium carbonate equivalent and 11.2 million tonnes of potash.  As a team we were very excited by this development, a recoverable resource provides additional confidence for a significant portion of the in-situ resource, and with additional work and economic data, could represent an expectation for an eventual brine reserve level.
  • Initiated a Preliminary Economic Assessment (“PEA”).  Following from the positive information learned with the recoverable inferred brine resource, we initiated a PEA for Diablillos on April 4, 2011.  The PEA will review the economic parameters for the development of a 10,000 to 15,000 tonne per annum lithium carbonate operation and management expects the PEA to be completed before calendar year end.  We are in the process of entering into various engagement letters with the appropriate consulting groups involved in this process and wish to express to shareholders that we will only be working with the industry’s top tier consultants to ensure the integrity of the work.

We are also working on a number of initiatives that we believe will help generate interest in the Rodinia story and that will ideally have a direct and positive impact on our share price.  Specifically:
  • Continue to Attract Top-Quality Professionals.  Over the past month, we have retained the services of Bob Cinq-Mars to advise on processing methodologies.  This was yet another significant addition for the Rodinia team as Bob comes with an extensive lithium and lithium processing background, but more importantly with direct experience with salars in Argentina having spent 20 years with FMC Lithium Division (“FMC”).  Our team already includes key professionals that helped successfully define and build lithium operations for FMC and for the Argentine government.  We believe this addition will solidify our processing capabilities, but more importantly highlights that top-quality industry professionals view Rodinia as having significant potential. 
In addition to adding Bob, we are in active discussions with a few other industry professionals that also boast impressive lithium resumes, and with a number of successful and well connected lithium-focused, end-market professionals that we hope to include as part of a Business Advisory Board for the Company or as additions to our Board of Directors.  In this last light, we recently added Xizhong Shi to our Board.  Mr. Shi is the CEO of Hong Kong Shanshan Resources Co. Ltd., a strategic investor in Rodinia and one of the world’s largest producers of materials used for the manufacturing of lithium ion batteries.  Mr. Shi is a graduate of Beijing University, the most prestigious post secondary institute in China, and has a track record of success that has made him a known and highly regarded figure in China.  Mr. Shi provides valuable insight into the end-market for lithium carbonate and is able to open doors for Rodinia to meet many other key industry players.
  • Working to Initiate Equity Research Coverage.  A key part of getting the Rodinia story out to the market and to attracting new investors is coverage from third party equity research analysts.  We have been fortunate over the past 16 months to have developed a following and support from Byron Capital Markets, however we believe that more research coverage is vital to getting our story out, and we are working diligently to try and attract the attention of these analysts.   We believe in the coming weeks or months we will see the results of these efforts through various initiation reports.  To date we have spent one-on-one time with over eight analysts; five analysts have spent time visiting our project sites and another three are in the process of scheduling visits.
  • Continuing our Broad Marketing Initiatives.  Throughout the past two years we met with a number of institutional investors across the Americas, Europe and Asia.  We have continued to meet with new institutional accounts and with a number of retail groups, but understand that we have really only begun to scratch the surface of potential investors and supporters.  Over the summer months, we plan to be very active marketing Rodinia to new potential investors and to those who saw us before our recent Diablillos advancement efforts.  We have a compelling story to tell and the more we tell it, the more support we will see in the market.
  • Advancing Relationship with Shanshan and Other Strategic Investors.  During 2010, Rodinia was successful in establishing a relationship and exploration funding from Shanshan Enterprise, based in Ningbo, China.  As previously mentioned, Shanshan is China’s largest lithium battery materials provider and one of the largest end users of lithium products in the country.  Over the past few months, and in the weeks to come, Rodinia’s senior management team will be travelling to China in order to meet with Shanshan to further our strategic releationship.  It is our expectation that both Rodinia and Shanshan can mutually benefit from a closer working relationship consisting of broader cooperation developing the Diablillos deposit into an operating mine.
We also continue to receive inbound calls from other strategic end-users of lithium carbonate.  These inquiries range from well-known international businesses, to smaller cutting-edge technology companies.  We actively engage with all interested groups and are hopeful that in the near-to-mid-term we can broaden our off-take horizons while securing additional development capital.
As a team, our top priority is the successful development of our lithium projects.  An extension of this priority is making sure that our efforts are accurately reflected in our share price.  While we are disappointed with recent trading we maintain our positive attitude and are working hard to develop the company and to unlock value for shareholders.  With the work we have completed since the last financing, the news flow that will follow our recent initiatives (drill results, processing work, etc.), and support from new and existing shareholders, we remain highly motivated to continue to grow the Company and execute our strategic plan.  As we progress, we will continue to update you through our website and press releases.
Thanks again for your continued support.
Sincerely,

RODINIA LITHIUM INC.

Farhad Abasov – Executive Chairman
Aaron Wolfe – VP, Corporate Development
William Randall – President & CEO
Jennifer Wagner – Corporate Secretary
Ryan Ptolemy – Chief Financial Officer
Investor Cubed Inc. – Investor Relations

Articles:  6 Reasons to consider Rodinia LIthium for your portfolio

Enhanced by Zemanta

Monday, July 11, 2011

San Gold Reports Record Quarterly Gold Production and Provides Notice of Second Quarter 2011 Financial Results Conference Call

gold cast barImage by hto2008 via Flickr
SOURCE: San Gold Corporation
July, 2011



BISSETT, MB--(Marketwire - Jul 7, 2011) - San Gold Corporation (TSX: SGR) (OTCQX: SGRCF) ("San Gold" or the "Company") reports preliminary operating results for the second quarter of 2011. The Company is also announcing that it plans to report second quarter 2011 financial results before market open on Monday, August 15, 2011, and that senior management will host a conference call that day at 11:00 am Eastern Standard Time.

Second Quarter 2011 Operating Results
In the second quarter of 2011, the Company's Rice Lake, Hinge, and 007 mines (the "Rice Lake Project") produced a quarterly record of 20,055 ounces of gold at a cash operating cost that is expected to be below the Company's full-year guidance of $825 per ounce of gold sold. Year-to-date production of 34,743 ounces is consistent with the Company's full-year production forecast of 80,000 ounces.

Commenting on these results, George Pirie, President and Chief Executive Officer of San Gold, stated, "I am very pleased with this quarter's operating results as they demonstrate that we continue to execute on our plan of growing the production profile and lowering the cost profile of the Rice Lake Project. In addition, we continue our aggressive exploration program, which is designed to significantly grow our mineral resource base."

Gold production in the second quarter of 2011 was approximately 118% higher than gold production of 9,188 ounces in second quarter of 2010 and 37% higher than gold production of 14,688 ounces in the first quarter of 2011. Gold production in the first half of 2011 increased 61% compared to gold production of 21,650 ounces in the first half of 2010.

Higher gold production in the second quarter of 2011 was primarily attributable to increased crushing and milling system capacity resulting in higher throughput relative to prior periods. Gold production in the second quarter of 2011 also benefited from approximately 80% of the milled tonnage being sourced from the generally lower cost and higher grade Hinge and 007 mines. The Hinge and 007 mines are expected to continue to be the primary source of ore at the Company's Rice Lake Mill for the foreseeable future.

During the second quarter of 2011, the Company milled ore at a record quarterly rate of approximately 1,260 tons per day for a total of 114,624 tons, an increase of 97% compared to the rate of 639 tons per day in the same period of 2010. In the second quarter of 2011, the average head grade of 6.34 grams of gold per tonne of ore ("g/t Au"), an increase of 9% relative to the average head grade of 5.82 g/t Au in the same period of 2010. The Company continues to have a substantial surface stockpile of approximately 25,000 tons of ore ahead of the crushing circuit.

Commenting on the improved quarterly operating results, Ian Berzins, Chief Operating Officer of San Gold, stated, "This quarter's record gold production is a direct result of nearly two years of successfully executing on our strategy of debottlenecking the operation, improving safety performance, and investing in new infrastructure and equipment. We continue to make incremental improvements at the Rice Lake Project."
Key operational metrics and production statistics for the second quarter of 2011 compared to the second quarter of 2010 and the first quarter of 2011 are presented in tables 1 and 2 at the end of this press release, respectively.

Notice of Second Quarter 2011 Financial Results Conference Call
The Company's senior management plans to host a conference call on Monday, August 15, 2011 at 11:00 am Eastern Standard Time to discuss the 2011 second quarter financial results, and to provide an update of the Company's operating, exploration, and development activities.
Participants may join the conference call by dialing 1 (888) 231-8191 or 1 (647) 427-7450 for outside Canada and the United States. The conference call will also be available by webcast at the following link: http://www.newswire.ca/en/webcast/viewEvent.cgi?eventID=3595460.
A recorded playback of the conference call can be accessed after the event until August 22, 2011 by dialing 1 (800) 642-1687 or 1 (416) 849-0833 for calls outside Canada and the United States. The pass code for the conference call playback is 81672417. The archived audio webcast will also be available on the Company's website at www.sangold.ca.

About San Gold
San Gold is an established Canadian-based gold producer, explorer, and developer that owns and operates the Hinge, 007, and Rice Lake mines near Bissett, Manitoba. The Company employs over 400 people and is committed to the highest standards of safety and environmental stewardship. The Company has over $45 million in cash and equivalents and is unhedged to the price of gold. As of June 30, 2011, San Gold has 310,491,175 common shares outstanding (320,861,811 shares fully diluted), which are traded on the Toronto Stock Exchange under the symbol "SGR" and on the OTCQX under the symbol "SGRCF".
Cautionary Non-GAAP Statements
The Company believes that investors use certain indicators to assess gold mining companies. They are intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared with Generally Accepted Accounting Principles ("GAAP"). "Cash operating costs" as used in this analysis is a non-GAAP term typically used by gold mining companies to assess the level of gross margin available to the Company per ounce of gold by subtracting these costs from the unit price realized during the period. This non-GAAP term is also used to assess the ability of a mining company to generate cash flow from operations. There may be some variation in the method of computation of "cash operating costs" as determined by the Company compared with other mining companies. In this context, "cash operating costs" reflects the per ounce cash costs allocated from in-process and dore inventory associated with ounces of gold sold in the period. "Cash operating costs" may vary from one period to another due to operating efficiencies, quantity of ore processed, grade of ore processed, and gold recovery rates.
Cautionary Note
No stock exchange, securities commission or other regulatory authority has approved or disapproved the information contained herein. This news release includes certain "forward-looking statements". All statements, other than statements of historical fact included in this release, including, without limitation, statements regarding forecast gold production, gold grades, recoveries, cash operating costs, potential mineralization, mineral resources, mineral reserves, exploration results, and future plans and objectives of the Company, are forward-looking statements that involve various risks and uncertainties. These forward-looking statements include, but are not limited to, statements with respect to mining and processing of mined ore, achieving projected recovery rates, anticipated production rates and mine life, operating efficiencies, costs and expenditures, changes in mineral resources and conversion of mineral resources to proven and probable mineral reserves, and other information that is based on forecasts of future operational or financial results, estimates of amounts not yet determinable and assumptions of management.
Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, using words or phrases such as "expects" or "does not expect", "is expected", "anticipates" or "does not anticipate", "plans", "estimates" or "intends", or stating that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved) are not statements of historical fact and may be "forward-looking statements." Forward-looking statements are subject to a variety of risks and uncertainties that could cause actual events or results to differ from those reflected in the forward-looking statements.
There can be no assurance that forward-looking statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from the Company's expectations include, among others, the actual results of current exploration activities, conclusions of economic evaluations and changes in project parameters as plans continue to be refined as well as future prices of precious metals, as well as those factors discussed in the section entitled "Other MD&A Requirements and Additional Disclosure and Risk Factors" in the Company's most recent quarterly Management's Analysis and Discussion ("MD&A"). Although the Company has attempted to identify important factors that could cause actual results to differ materially, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.
Exploration results that include geophysics, sampling, and drill results on wide spacings may not be indicative of the occurrence of a mineral deposit. Such results do not provide assurance that further work will establish sufficient grade, continuity, metallurgical characteristics, and economic potential to be classed as a category of mineral resource. A mineral resource that is classified as "inferred" or "indicated" has a great amount of uncertainty as to its existence and economic and legal feasibility. It cannot be assumed that any or part of an "indicated mineral resource" or "inferred mineral resource" will ever be upgraded to a higher category of resource. Investors are cautioned not to assume that all or any part of mineral deposits in these categories will ever be converted into proven and probable reserves.
Table 1: Second Quarter 2011 and 2010 Production Summary and Statistics (1,2)
Q2
2011
Q2
2010
Change
(#)
Change
(%)
Ore mined (tons) 119,745 63,024 56,721 90%
Ore milled (tons) 114,624 58,156 56,468 97%
Head grade (g/tonne Au) 6.34 5.82 0.52 9%
Ounces of gold produced (3) 20,055 9,188 10,867 118%
Ore mined per day (tons) 1,316 693 623 90%
Ore milled per day (tons) 1,260 639 621 97%
Mill recovery (%) 95% 93% 2 2%
(1) All amounts for Q2-2011 are preliminary and based on initial end of period estimates. Final adjustments may be required.
(2) Certain numbers may not compute due to the effects of rounding and truncation.
(3) Before final refinery settlements, which may result in increases or decreases to reported gold production.
Table 2: Year-to-Date Production Summary and Statistics (1,2)
Q2
2011
Q1
2011
Change
(#)
Change
(%)
YTD
Q2-2011
Ore mined (tons) 119,745 102,200 17,545 17% 221,945
Ore milled (tons) 114,624 82,792 31,832 38% 197,416
Head grade (g/tonne Au) 6.34 6.47 -0.13 -2% 6.40
Ounces of gold produced (3) 20,055 14,688 5,367 37% 34,743
Ore mined per day (tons) 1,316 1,136 180 17% 1,119
Ore milled per day (tons) 1,260 910 350 38% 1,091
Mill recovery (%) 95% 94% 1 1% 94%
(1) All amounts for Q2-2011 are preliminary and based on initial end of period estimates. Final adjustments may be required.
(2) Certain numbers may not compute due to the effects of rounding and truncation.
(3) Before final refinery settlements, which may result in increases or decreases to reported gold production.
The TSX or the OTCQX have not reviewed and do not accept responsibility for the adequacy or accuracy of this release.

Enhanced by Zemanta